Description
The loader is the final end of a project with an investment of 163 million dollars, in addition to the loader that concerns us was built a pier, an access bridge and 3.5 km of conveyor belt. This infrastructure is capable of transporting more than 2 thousand wet tons per hour of mineral concentrate. Five times more than the previous transport capacity. Thanks to this charger, the waiting time of ships from eight days to only hours is reduced.
Working scope
- Manufacture of electrical equipment
- Pre-installation of electrical room
- PLC Programming
- Scada for control and maintenance.
- Commissioning of installation.
Technical data
- MT connection, 10 Kv.
- Dry Three-Phase Transformer – ABB – 10 Kv / 460 V 60Hz – 630 KVA
- Retrofit of main motors with Multidrive ABB regenerativo, 460V;60Hz
- Elevation; 150KW; (STARTING WITH VARIATOR) 460V;60Hz; 1200rpm; 3P
- Translation Tape; 15 KW; (STARTING WITH VARIATOR) 460V;60Hz; 1200rpm; 3P
- Translation: 12 u.d x7.5KW;(STARTING WITH VARIATOR) 460V; 60Hz;1800 rpm; 3P
- Nozzle lift; 11 Kw; (DIRECT START) 460V; 60Hz;1800 rpm; 3P
- PLC Siemens 300 control
- Scada WinCC flexible
- Communication with port system with OPC